Periodic maintenance

Draft

Maintenance intervals will be finalized during commissioning according to the site's usage intensity.

CheckIntervalNote
Emergency stop function test (all buttons)At the start of every shiftVerify that both channels stop the system
Residual current device test buttonMonthlyRCDs inside the cabinet
Holding brake function checkMonthlyThe brake must engage when power is removed
Slip ring visual inspectionEvery 3 monthsCable service loops and strain relief clamps
Protective earth (PE) continuityAnnually and after slip ring maintenanceCabinet → outermost rotating stage, measured at two different gimbal positions
Braking resistor cooling clearance and cleanlinessEvery 6 monthsThere must be no dust accumulation around the resistor
After slip ring maintenance

After any slip ring maintenance, the system must not be operated until the emergency stop, STO and PE continuity tests have been repeated at more than one gimbal position.